Prairie says DLE site preparation advancing


Staff reporter

Australian microcap Prairie Lithium says it has recovered first brine from the Duperow Formation in Saskatchewan, Canada, for metallurgical testing as it prepares a pad for phase-one operations.

The company has a C$6.3 million interest-free Prairies Economic Development Canada loan to advance the project and a binding offtake agreement with Hydro Lithium for phase-one output,

It said the test well and production pad works added to existing power and other infrastructure at the site, including a four-column commercial-scale direct lithium extraction (DLE) unit, production and disposal wells, and an administration building.

“Successfully bringing brine to the surface from our production well is an important operational milestone for Prairie Lithium,” executive chairman Paul Lloyd said.

“Completing the site expansion, civil works and re-entry program ahead of the Canadian winter is another positive step in preparing pad 1 for the next stages of development. The recovered brine will now be used for continued metallurgical testing as we advance our phase one plans.

“Considering the current commodity price environment and broader market conditions, the company is taking a measured and disciplined approach to capital allocation. We remain focused on progressing critical-path construction activities at site while carefully managing expenditure to preserve the project’s long-term value and flexibility.

“We remain committed to advancing the Prairie Lithium project.”

A late 2023 prefeasibility study put a circa-US$290 million pre-production capital cost on a three-well operation producing up to 6000 tonnes per annum of lithium carbonate-equivalent at a $2820/t LCE projected operating cost.

The company had A$4.4 million cash and cash equivalents at hand at the end of September this year.

Its share price finished up 25% today at A0.5c, capitalising Prairie at circa-$14.5 million.

 