Generation says Marathon costs on track


Staff reporter

Toronto-listed Generation Mining says it is “at or below” budget cost estimates in last year’s updated prefeasibility study on its circa-US$700 million Marathon copper-palladium project in Ontario after passing the halfway mark with procurement commitments.

“Orders are now in place for all of the project’s major long-lead equipment, work is well under way at site and the project remains on track,” the company said this week.

“Forecast cost at completion remains within the construction budget. Savings on equipment purchases have offset expected higher fuel costs, meaning the contingency portion of the construction budget remains intact.”

Generation said it was working closely with equipment manufacturer Metso on Marathon’s processing plant, which would have a semi-autogenous grinding mill with the “full 10.1 million tonnes per year of capacity from the outset” instead of the 8.9Mtpa outlined in years 1-3 in early feasibility work. Generation said “smarter mill design”, including the bigger SAG mill “gives Marathon its full planned processing capacity of 10.1Mtpa from start-up, removes the need for a pebble crusher and avoids approximately C$12 million in future expansion costs”.

The company has ordered Marathon’s primary crusher, SAG and ball mills from Metso and says discussions are progressing on flotation equipment and pumps, as well as a long-term service agreement.

It has also ordered mobile mining equipment, transformers and substation plant and has mining contractor L Fournier et Fils doing earthworks. EPCM contractor Ausenco is said to be about a third of the way into Marathon’s detailed engineering.

“Our focus is on making decisions today that improve both how we build Marathon and how it performs for years to come,” Generation vice president projects, Clinton Swemmer, said.

“The larger SAG mill is a good example: it simplifies the plant, gives us full capacity from start-up and avoids future expansion costs.

“Together with our progress on engineering and earthworks at site, decisions like this are focusing the project team on a clear project schedule.”

Generation says it has committed more than C$500 million of procurement spend for Marathon. The company this year finalised $1.3 billion of project equity, debt and streaming finance.

It has a current market capitalisation of about C$250 million.

 